Background

Excavations dug in London city centre began to fill with ground and surface water runoff. With works needing to continue in poor weather conditions, these excavations needed to be dewatered quickly whilst remaining compliant with the sites discharge consent.

The Overall Objective

The restricted site required a compact solution to be able to suitably meet their needs whilst ensuring work could continue without any disruption.

Solution

Siltbuster installed a 2” submersible pump in conjunction with a Siltbuster HB20 to dewater the excavations and enable discharge to the mains sewer.

Additionally Siltbuster HB20 was fitted with an impeller flowmeter to allow the site to record the volume of water discharged (a requirement of their discharge permit).

Back to top
Cost-efficiency, cost savings and discharge compliance! A Siltbuster solution consisting of a Chemical Mix Tank and… https://t.co/nUDuBNcVfU
2:52 PM 15 Oct 2020 Join the conversation
Autumn greetings from Paris where Siltbuster systems are hard at work at numerous locations throughout the gigantic… https://t.co/bMbHGDKuuD
2:49 PM 15 Oct 2020 Join the conversation
"An overview of surface water management in the construction sector and an introduction to Siltbuster Ltd". Regist… https://t.co/5ZHcbwJQkU
8:45 AM 9 Oct 2020 Join the conversation
#Siltbuster HQ is very busy, including loading and dispatch of 3 full lorries heading for the North East with final… https://t.co/uLmtExWzEl
8:14 AM 9 Sep 2020 Join the conversation
A Siltbuster in the sky! The image really shows how space efficient our systems are with a Siltbuster unit hard at… https://t.co/5dYzfYqgVn
12:50 PM 10 Aug 2020 Join the conversation