London City Centre Dewatering

Client:Skanska PLC

Background

Excavations dug in London city centre began to fill with ground and surface water runoff. With works needing to continue in poor weather conditions, these excavations needed to be dewatered quickly whilst remaining compliant with the sites discharge consent.

The Overall Objective

The restricted site required a compact solution to be able to suitably meet their needs whilst ensuring work could continue without any disruption.

Solution

Siltbuster installed a 2” submersible pump in conjunction with a Siltbuster HB20 to dewater the excavations and enable discharge to the mains sewer.

Additionally Siltbuster HB20 was fitted with an impeller flowmeter to allow the site to record the volume of water discharged (a requirement of their discharge permit).

Back to top
Merry Christmas from Siltbuster and SPS! Can you spot the squidgy Siltbuster decorations on our tree? https://t.co/ND5al47lAF
1:12 PM 12 Dec 2018 Join the conversation
The product of 2 years worth of research and development between market leaders within their respective fields, the… https://t.co/pCfwxPZi4D
4:38 PM 19 Nov 2018 Join the conversation
The Siltbuster CPD training courses are coming to Chelsea Football Stadium on 21st Nov. Book online now… https://t.co/VaWZjH8KhL
1:40 PM 2 Nov 2018 Join the conversation
Our next Managing Water Pollution on Construction Sites CPD training course is coming to Liverpool on the 31st Oct.… https://t.co/s4tnaRgSVZ
7:59 AM 16 Oct 2018 Join the conversation
We were pleased to raise money for @macmillancancer by holding a coffee morning last week. The cakes from Claire an… https://t.co/AT1KWGtjT3
8:42 AM 8 Oct 2018 Join the conversation