CPC Civils Cofferdam Installation

Client:CPC Civils
Discharge Point:Surface Watercourse
Flow Rate:60m³/hr

Background

CPC Civils were carrying out the installation of a sheet piled cofferdam. During construction dirty water infiltrated the work area and required dewatering before it could be safely discharged into the environment.

The Overall Objective

CPC Civils required a treatment system to deal with slow settling solids as a result of the construction work being carried out.

Solution

Siltbuster installed a 2 stage chemical dosing system consisting of 1 MT8 chemical mix tank and 1 HB50 Lamella Clarifier with a flow rate of between 1-60m³/hr, to remove the particulates before finally being discharged further downstream.

Back to top
Cost-efficiency, cost savings and discharge compliance! A Siltbuster solution consisting of a Chemical Mix Tank and… https://t.co/nUDuBNcVfU
2:52 PM 15 Oct 2020 Join the conversation
Autumn greetings from Paris where Siltbuster systems are hard at work at numerous locations throughout the gigantic… https://t.co/bMbHGDKuuD
2:49 PM 15 Oct 2020 Join the conversation
"An overview of surface water management in the construction sector and an introduction to Siltbuster Ltd". Regist… https://t.co/5ZHcbwJQkU
8:45 AM 9 Oct 2020 Join the conversation
#Siltbuster HQ is very busy, including loading and dispatch of 3 full lorries heading for the North East with final… https://t.co/uLmtExWzEl
8:14 AM 9 Sep 2020 Join the conversation
A Siltbuster in the sky! The image really shows how space efficient our systems are with a Siltbuster unit hard at… https://t.co/5dYzfYqgVn
12:50 PM 10 Aug 2020 Join the conversation