Bam Nuttall New Electric Substation

Client:BAM Nuttall
Discharge Point:Surface Watercourse
Flow Rate:50m³/hr

Background

In Blackhillock, Moray, Scotland Bam Nuttall are carrying out the construction of a new £120m electricity substation scheduled for completion in 2019. This will be a major reinforcement of the transmission network serving the north of Scotland, enabling proposed wind, wave and tidal generation sites to connect.

The Overall Objective

As work was carried out, topsoil’s were stripped and left exposed to rainfall and surface water runoff. Excavations quickly began to fill with water and clay from the surrounding landscape and required chemical treatment before being released off site.

Solution

Two Siltbuster chemical dosing units were deployed and commissioned at short notice allowing site to continue with the work with little disruption.

Back to top
A multitasking green #Siltbuster! A bespoke iHB20R is going through final assembly and testing in our workshop befo… https://t.co/hEApXLG7to
12:08 PM 28 Oct 2020 Join the conversation
Cost-efficiency, cost savings and discharge compliance! A Siltbuster solution consisting of a Chemical Mix Tank and… https://t.co/nUDuBNcVfU
2:52 PM 15 Oct 2020 Join the conversation
Autumn greetings from Paris where Siltbuster systems are hard at work at numerous locations throughout the gigantic… https://t.co/bMbHGDKuuD
2:49 PM 15 Oct 2020 Join the conversation
"An overview of surface water management in the construction sector and an introduction to Siltbuster Ltd". Regist… https://t.co/5ZHcbwJQkU
8:45 AM 9 Oct 2020 Join the conversation
#Siltbuster HQ is very busy, including loading and dispatch of 3 full lorries heading for the North East with final… https://t.co/uLmtExWzEl
8:14 AM 9 Sep 2020 Join the conversation