BAM Nuttall M1 Widening Scheme

Client:BAM Nuttall

Background

BAM Nuttall were carrying out work as part of the M1 widening scheme. During works our client was granted a permit to discharge 2 m³/day of treated concrete washwater into a motorway drainage channel which linked into a surface watercourse.

The Overall Objective

Washdown waters from the onsite batching plant and the 7 no. lorries that were feeding the slipform paving machines on the motorway, were held in a catchpit.

Solution

At the end of each day 2 m³ of water was transferred into the water holding tank and treated using the pHD unit ready for discharge to the surface watercourse in the morning.

Back to top
See this and more at outdoor stand DA1 https://t.co/GunKIXwcMe
8:57 AM 7 Jun 2019 Join the conversation
Visit Siltbuster at the Plantworx show, 11th – 13th June at East of England Arena Peterborough. Our large outdoor s… https://t.co/VHxIOSJFCM
9:25 AM 5 Jun 2019 Join the conversation
SPS have commissioned a new effluent treatment plant for Tata Steel. Read about the project in Machinery Market:… https://t.co/Dz4YsVrqnm
9:12 AM 22 May 2019 Join the conversation
Siltbuster is presenting at the next Geotex seminar in Duxford, Cambridgeshire on the 15th May. Register for your f… https://t.co/lPIbvmmMmo
9:33 AM 7 May 2019 Join the conversation
The next Siltbuster CPD training course is coming to Edinburgh Zoo this month on the 22nd May. Book your place onli… https://t.co/zMUGwLfsN9
12:41 PM 1 May 2019 Join the conversation