Client:Forkers
Flow Rate:80m³/hr

Background

Forkers are carrying out construction work to upgrade and install a new pump station in Stafford, West Midlands. The work is being carried out as part of a £5m investment in the area to cope with the increased residential and commercial growth in the area.

The Overall Objective

Due to excavation work carried out before the installation of the new pumping station, groundwater ingress occurred which required treatment before safe discharge to a nearby surface water course.

Solution

Siltbuster provided a 3 stage chemical treatment system which was capable of treating flows of up to 80m³/hr whilst neutralising the high pH water.

Back to top
Some Siltbusters looking good in the sun! These two lorries are heading for a large infrastructure project in Somer… https://t.co/BmZzh1wz6g
1:36 PM 19 Apr 2018 Join the conversation
SPS and Suez cooperate to deliver clean water for Italian fertilizer manufacturer under highly variable conditions… https://t.co/WtqxqjrdAJ
3:52 PM 17 Apr 2018 Join the conversation
Glad to be part of the event and looking forward to some interesting conversations. https://t.co/OZFOOrExk0
12:02 PM 11 Apr 2018 Join the conversation
Great feedback from our recent win. https://t.co/zb7TtkObao https://t.co/0rhjSppOfZ
1:24 PM 27 Mar 2018 Join the conversation