Malin Floors industrial Concrete Floors

Client:Malin Floors Ltd

Background

Malin Floors Ltd were pouring circa 500m³ of concrete per day which resulted in circa 83 chute wash downs of the concrete truck mixer chutes.

The Overall Objective

The client was discharging to ground with a surface water course following the site boundary at the bottom of the site and required a solution to ensure the water was safe prior to discharge.

Solution

Washdown waters from the concrete truck mixer chutes were fed in to a lined 6 yard skip. Once the cementitious material in the reception skip had settled from suspension, supernatant water was transferred in to a second 6 yard skip for the alkaline waters to be neutralised by the Siltbuster pHD.

Back to top
Some Siltbusters looking good in the sun! These two lorries are heading for a large infrastructure project in Somer… https://t.co/BmZzh1wz6g
1:36 PM 19 Apr 2018 Join the conversation
SPS and Suez cooperate to deliver clean water for Italian fertilizer manufacturer under highly variable conditions… https://t.co/WtqxqjrdAJ
3:52 PM 17 Apr 2018 Join the conversation
Glad to be part of the event and looking forward to some interesting conversations. https://t.co/OZFOOrExk0
12:02 PM 11 Apr 2018 Join the conversation
Great feedback from our recent win. https://t.co/zb7TtkObao https://t.co/0rhjSppOfZ
1:24 PM 27 Mar 2018 Join the conversation