Background

In readiness for the construction of a new hotel complex at Heathrow Airport, ECS are conducting ground preparation works and service diversions at a highly constrained and complex site.

The Overall Objective

As part of trenching works being carried out through contaminated ground. All water needed to be collected in a series of networks and treated prior to discharge in order to meet Heathrow Airport’s strict water drainage quality criteria.

Solution

Siltbuster visited the site and planned the works to establish the correct treatment requirements to deal with the flow rates and enable contaminant removal.

Siltbuster installed an HB50 unit to ensure the water could be successfully treated and subsequently discharged from site. Throughout the project Siltbuster provided regular support to ensure any problems could be solved quickly.

Treated water was regularly sampled by Heathrow’s laboratory service and every sample successfully passed its quality criteria.

Back to top
Some Siltbusters looking good in the sun! These two lorries are heading for a large infrastructure project in Somer… https://t.co/BmZzh1wz6g
1:36 PM 19 Apr 2018 Join the conversation
SPS and Suez cooperate to deliver clean water for Italian fertilizer manufacturer under highly variable conditions… https://t.co/WtqxqjrdAJ
3:52 PM 17 Apr 2018 Join the conversation
Glad to be part of the event and looking forward to some interesting conversations. https://t.co/OZFOOrExk0
12:02 PM 11 Apr 2018 Join the conversation
Great feedback from our recent win. https://t.co/zb7TtkObao https://t.co/0rhjSppOfZ
1:24 PM 27 Mar 2018 Join the conversation