Background

Garston Gasworks were known for producing carburetted water gas, with coal gas being produced from 1921. The works later had an oil pipeline to the docks.

the works has not been in use since 2008 and was due to be decontaminated and demolished to make space for redevelopment in the area.

The Overall Objective

Erith Contractors were tasked with dewatering 2 gasholder basins to allow for decontamination of the site and subsequent removal of the existing structures in place. The site would then be back filled and used for redevelopment.

Solution

Siltbuster provided Erith with their FB50 plus a CM400 to dewater the site and settle mineral solids before discharging the water safely to the surrounding environment.

Back to top
SPS will be at the Ricoh arena next week, exhibiting at this year's @FDBexpo (stand s02). Register for FREE now at… https://t.co/Z5M6bpWr99
3:30 PM 25 Sep 2018 Join the conversation
SPS will be at next month's Food and Drink show in Coventry with Dave Gaskill speaking. Register to attend for free… https://t.co/RV0NNaHCxv
9:46 AM 17 Sep 2018 Join the conversation
Our 1 day Managing Water Pollution on Construction Sites CPD training course is coming to the Welsh capital on the… https://t.co/1I1q4iZyL7
1:06 PM 10 Sep 2018 Join the conversation
Siltbuster can help advise. For more information read our post: https://t.co/uF1rKwwCs7 https://t.co/GGR01lLw0T
11:19 AM 4 Sep 2018 Join the conversation
We're excited for this weekend's raft race on the beautiful river Wye. This year we're entering a joint team with o… https://t.co/mv4ti6tmr4
11:58 AM 31 Aug 2018 Join the conversation