Garston Gasworks

Client:Erith Contractors
Flow Rate:25m³/hr

Background

Garston Gasworks were known for producing carburetted water gas, with coal gas being produced from 1921. The works later had an oil pipeline to the docks.

the works has not been in use since 2008 and was due to be decontaminated and demolished to make space for redevelopment in the area.

The Overall Objective

Erith Contractors were tasked with dewatering 2 gasholder basins to allow for decontamination of the site and subsequent removal of the existing structures in place. The site would then be back filled and used for redevelopment.

Solution

Siltbuster provided Erith with their FB50 plus a CM400 to dewater the site and settle mineral solids before discharging the water safely to the surrounding environment.

Back to top
Merry Christmas from Siltbuster and SPS! Can you spot the squidgy Siltbuster decorations on our tree? https://t.co/ND5al47lAF
1:12 PM 12 Dec 2018 Join the conversation
The product of 2 years worth of research and development between market leaders within their respective fields, the… https://t.co/pCfwxPZi4D
4:38 PM 19 Nov 2018 Join the conversation
The Siltbuster CPD training courses are coming to Chelsea Football Stadium on 21st Nov. Book online now… https://t.co/VaWZjH8KhL
1:40 PM 2 Nov 2018 Join the conversation
Our next Managing Water Pollution on Construction Sites CPD training course is coming to Liverpool on the 31st Oct.… https://t.co/s4tnaRgSVZ
7:59 AM 16 Oct 2018 Join the conversation
We were pleased to raise money for @macmillancancer by holding a coffee morning last week. The cakes from Claire an… https://t.co/AT1KWGtjT3
8:42 AM 8 Oct 2018 Join the conversation