BAM Nuttall M1 Widening Scheme

Client:BAM Nuttall

Background

BAM Nuttall were carrying out work as part of the M1 widening scheme. During works our client was granted a permit to discharge 2 m³/day of treated concrete washwater into a motorway drainage channel which linked into a surface watercourse.

The Overall Objective

Washdown waters from the onsite batching plant and the 7 no. lorries that were feeding the slipform paving machines on the motorway, were held in a catchpit.

Solution

At the end of each day 2 m³ of water was transferred into the water holding tank and treated using the pHD unit ready for discharge to the surface watercourse in the morning.

Back to top
Some Siltbusters looking good in the sun! These two lorries are heading for a large infrastructure project in Somer… https://t.co/BmZzh1wz6g
1:36 PM 19 Apr 2018 Join the conversation
SPS and Suez cooperate to deliver clean water for Italian fertilizer manufacturer under highly variable conditions… https://t.co/WtqxqjrdAJ
3:52 PM 17 Apr 2018 Join the conversation
Glad to be part of the event and looking forward to some interesting conversations. https://t.co/OZFOOrExk0
12:02 PM 11 Apr 2018 Join the conversation
Great feedback from our recent win. https://t.co/zb7TtkObao https://t.co/0rhjSppOfZ
1:24 PM 27 Mar 2018 Join the conversation