American Embassy Construction

Client:O'keefe Contractors

Background

During the construction of civil works at the American Embassy site in London by O’keefe Contractors, solid laden water along with free phase hydrocarbon were encountered onsite.

Ground was broken on November 13, 2013, and the building is expected to be complete by 2017.

 

The Overall Objective

Siltbuster were tasked with dealing with two problems, the first was to remove suspended solids from the water onsite and secondly to remove the hydrocarbon to allow for safe discharge offsite.

 

Solution

Siltbuster installed its HB50-OWS (Oil Water Separator), to effectively treat the suspended solids and remove the free phase hydrocarbon by skimming it off and safely capturing it before removal from site.

 

Back to top
Merry Christmas from Siltbuster and SPS! Can you spot the squidgy Siltbuster decorations on our tree? https://t.co/ND5al47lAF
1:12 PM 12 Dec 2018 Join the conversation
The product of 2 years worth of research and development between market leaders within their respective fields, the… https://t.co/pCfwxPZi4D
4:38 PM 19 Nov 2018 Join the conversation
The Siltbuster CPD training courses are coming to Chelsea Football Stadium on 21st Nov. Book online now… https://t.co/VaWZjH8KhL
1:40 PM 2 Nov 2018 Join the conversation
Our next Managing Water Pollution on Construction Sites CPD training course is coming to Liverpool on the 31st Oct.… https://t.co/s4tnaRgSVZ
7:59 AM 16 Oct 2018 Join the conversation
We were pleased to raise money for @macmillancancer by holding a coffee morning last week. The cakes from Claire an… https://t.co/AT1KWGtjT3
8:42 AM 8 Oct 2018 Join the conversation