Alun Griffiths were completing construction of a new road in the Cross Hands area of West Wales. With 11 hectares of land exposed during one of the wettest periods of 2014, a large purpose built attenuation pond quickly filled with surface water runoff.

The Overall Objective

As the weather continued to deteriorate, more solid laden water run off seeped into the lagoon. To avoid causing pollution, Siltbuster were tasked with treating the water.

Solution

Siltbuster installed a 2 stage flow proportional chemical treatment system at short notice, capable of achieving a flow rate of up to 100m³/hr. The digital dosing equipment used, eliminated any pollution risks and the water standards achieved were among the highest standards.

Back to top
We're at the #EWWM conference today and tomorrow. Drop by for a chat about DAF, MBBR and Lamella water treatment so… https://t.co/WRc15K09lJ
9:58 AM 17 Jul 2018 Join the conversation
A few places remaining on the Siltbuster 2-day Environmental Professionals CPD course in Reading 18/19 July. Book n… https://t.co/OqWZhuWCfb
9:26 AM 3 Jul 2018 Join the conversation
Another batch of HB50Es are ready and on their way to our partner Telstar in France to further support the surface… https://t.co/HBXJcNat1o
2:16 PM 28 Jun 2018 Join the conversation
Download your free copy of Siltbuster's white paper explaining the EA's Regulatory Position Statement – “Temporary… https://t.co/rKmmA0d1NS
10:41 AM 22 Jun 2018 Join the conversation
We’ve got new positions (Senior Process Design Engineer and Technical Sales Engineer – Municipal) on our website… https://t.co/gs1qEKjqZX
9:22 AM 15 Jun 2018 Join the conversation