Airbus Manufacturing Facility

Client:Morgan Sindall

Background

Airbus’s improvement program appointed Morgan Sindall to undertake the construction of the 52,000m² manufacturing site for the manufacture of wings for the new Airbus A350 and A380.

The Overall Objective

The site had high-level groundwater issues and is within an area regulated by the Environment Agency therefore allowing high pH water to seep into the ground was not an option.

Solution

At first a Siltbuster RCW unit was introduced to site in March 2009. Two more were soon in place to control and treat washwater generated on-site, with a further two made available for use when required during larger concrete pours. During the pouring of the machine bases, truck movements peaked at 283 over the course of just one weekend, necessitating the use of four RCW units at once.

Back to top
SPS will be at the Ricoh arena next week, exhibiting at this year's @FDBexpo (stand s02). Register for FREE now at… https://t.co/Z5M6bpWr99
3:30 PM 25 Sep 2018 Join the conversation
SPS will be at next month's Food and Drink show in Coventry with Dave Gaskill speaking. Register to attend for free… https://t.co/RV0NNaHCxv
9:46 AM 17 Sep 2018 Join the conversation
Our 1 day Managing Water Pollution on Construction Sites CPD training course is coming to the Welsh capital on the… https://t.co/1I1q4iZyL7
1:06 PM 10 Sep 2018 Join the conversation
Siltbuster can help advise. For more information read our post: https://t.co/uF1rKwwCs7 https://t.co/GGR01lLw0T
11:19 AM 4 Sep 2018 Join the conversation
We're excited for this weekend's raft race on the beautiful river Wye. This year we're entering a joint team with o… https://t.co/mv4ti6tmr4
11:58 AM 31 Aug 2018 Join the conversation